Kyiv region Projects

Euro Finance Ltd. LLC

  • Electrical steel-casting complex in Bila Tserkva
    The comprehensive support of the project concerning the construction of the power supply scheme for the electric rolling mill with 195.5 MW connected electrical capacity.
    2006-2009
 

NSC Olimpiyskiy

  • CHPP-5 in Kyiv
    Design works on rehabilitation of 110/35 kV outdoor switchgear of combined heat and power plant CHPP-5 (Kyivenergo), obtaining of a positive conclusion from the State Enterprise Ukrderzhbudekspertyza.
    2011

Pidriad Production Cooperative

  • The multistoried residential estate in Hatne
    The comprehensive support of the project concerning the construction of the power supply scheme for the multistoried residential estate.
    2007-2008
 

Vidkrytyi Prostir MC LLC

  • The cottage settlement in Roslavychi
    Feasibility study preparation of the external power supply scheme for the cottage settlement.
    Development of the 110/35/10 kV Prostir substation construction project of with 110, 35, 10 kV cable lines.
    2011

Mriya-Invest LLC

  • The shopping and entertainment mall in Kyiv
    The comprehensive support of the project concerning the designing and construction of the power supply scheme for the shopping and entertainment mall.
    2008-...
 

Liko-Holding LLC

  • The residential complex in Kyiv
    Feasibility study preparation of the external power supply scheme for the residential complex.
    2011

Slavutich Carlsberg Group LLC

  • The brewery in Kyiv
    Consulting on feasible measures to cut the brewery’s electricity bills.
    2009
 

Konkord-Trade LLC

  • The shopping-mall in Kyiv
    Designing of the external power supply scheme for the shopping-mall.
    2011

PJSC Kyivoblenergo

  • 10/0.4 kV power distribution station in Yahotyn
    Detailed engineering related to the 10 kV power grids along with construction of 10/0.4 kV switchgear.
    2009-2010
  • 110/35/10 kV Kniazhychi substation
    Detailed engineering related to the "Rehabilitation of the phase-differential protection at the 110/35/10 kV Kniazhychi substation".
    2010
  • 110/35/10 kV Boryspil substation
    Detailed engineering related to the "Rehabilitation of the 110/35/10 kV Boryspil substation", the capacitance current compensation of the II 10 kV busbar.
    2010
 

PJSC Kyivenergo

  • CHPP-5 in Kyiv
    Detailed engineering related to the rehabilitation of the 110 kV combined heat and power plant CHPP-5 – Darnytsya CHPP transit.
    2011-...
  • 110/10 kV Universytetska substation
    Development of the project (Project Study and Detailed Design stages) for the construction of the 110/10 kV Universytetska substation with two 110 kV cable lines.
    2011-2012
  • 110/10 kV Vatutinska substation
    Detailed engineering related to the construction of the 110/10 kV Vatutinska substation with Desnianska – Vatutinska 110 kV cable line.
    2011-2012

Ukrzhytlobudinvest LLC

  • The multistoried residential estate in Sofiivska Borshchahivka
    Managing the project of the power supply scheme construction for the multistoried residential estate and it’s interconnection to the power grid.
    2009-2011
 

CJSC Nest-Hanner

  • The multifunctional public facility in Kyiv
    The full range of design works on the power supply scheme construction with the total capacity of 12 MW and the public facility interconnection to the power grids of Kyivenergo.
    2011

Prominvestgroup-1 LLC

  • The hotel with an underground parking in Kyiv
    The full range of design works on the power supply scheme construction and the hotel complex interconnection to the power grid with the total capacity of 3.1 MW.
    2010
 

Boryspil IA SE

  • Boryspil airport
    Detailed engineering related to the rehabilitation of relay protection, diesel generator replacement and 10 kV cable lines laying. Support with approval of this work by all the concerned entities.
    2012-2013

LNK LLC

  • Power plant operating on the landfill gas obtained from municipal solid waste landfill 5 in Pidhirtsi
    The full range of design works on the power plant construction. The installed generating capacity is 4 425 kW.
    2010-2011
 

Biogasenergo LLC

  • 18 MW Thermal power plant in Ivankiv
    Turn-key 18 MW TPP construction project. Metropoliya Group acts as a general contractor and arranges all works related to the object construction: designing and documentation coordination, permits, procurement, supplies, management, consturction and comissioning.
    2013-2015

Ukrtransgas Affiliated Company of National Joint Stock Company Naftogaz of Ukraine

  • Yahotyn compressor station
    Feasibility study preparation "External Power Supply for Yahotyn Compressor Station on the ShKD, ShPK, EDK and the EKK gas pipelines". Support with approval of this work by all the concerned entities.
    2011
 


Bila Tserkva 1 Industrial Park LLC

  • Industrial Park at Bilotserkivskyi district, Kyiv Region
    Development of Feasibility study for External Power Supply Scheme and development of design (Design and Work stages) on construction of 110/10 kV S/S and 110 kV OHL for electrical power supply to 35 MW Industrial Park.
    2016-2017

Boryspil IA SE

  • Boryspil Airport
    Correction of Detailed Design on 10 kV cable laying to TP-1012 and RP-39 due to necessity to allocate two construction stages.
    2016-2017
 

Dymerska Solar Power Plant-1 LLC

  • 50 MW SPP, Velyka Dymerka
    Development of Detailed Design of 6 MW SPP (1st construction stage) in the area near Bogdanivka village and Velyka Dymerka town (Brovary District, Kyiv Region), development of feasibility study on adjusting of 50 MW SPP interconnection scheme, development of Detailed Design of SPP interconnection scheme (Coca-Cola S/S rehabilitation and construction of new OHLs), obtaining of construction permit.
    2016-2017